News

Westinghouse to supply new steam generators for Surry nuclear plant : Corporate - World Nuclear News

World Nuclear News · last updated

Westinghouse to supply new steam generators for Surry nuclear plant : Corporate - World Nuclear News

Westinghouse to supply new steam generators for Surry nuclear plant

17 May 2023

Westinghouse Electric Company has signed a contract with Dominion Energy to design, engineer and manufacture six replacement steam generators for Surry nuclear power station in Virginia in the USA.
The Surry units began commercial operation in the early 1970s (Image: Dominion)

The deal anticipates the steam generators being delivered from 2028 for installation beginning in 2029. The replacements support Dominion's Subsequent Licence Renewal programme to extend the lifetime of Surry units 1 and 2 into the 2050s. It follows a 2021 contract between Dominion and Westinghouse for a major Instrumentation & Control upgrade.

The steam generators will be fabricated at Westinghouse's facility in Monfalcone, Italy, and are based on the company's original F-Series units, with "multiple enhancements to maintain an industry leading best in-service performance".

Dan Stoddard, senior vice president and chief nuclear officer at Dominion, said: "Our long-term partnership with Westinghouse supports our efforts to extend Surry’s nuclear energy production for decades to come. Our Surry nuclear station operates year-round at more than 93% capacity, providing our customers with around-the-clock clean, reliable, and affordable energy."

Dan Sumner, president of operating plant services for Westinghouse, said: "These industry-leading steam generators will help Dominion deliver safe and efficient nuclear energy into the middle of the 21st century. We are proud to continue supporting Dominion’s modernisation efforts."

In 2021, the US Nuclear Regulatory Commission approved an application by Dominion Energy for a 20-year extension to the operating licences of the two Surry units, enabling the pressurised water reactors to each operate for 80 years, until 2052 and 2053 respectively.

Surry 1 began commercial operation in 1972 and Surry 2 in 1973, and were originally licensed to operate for 40 years. The units' licences were renewed for 20 additional years of operation in March 2003 before the subsequent renewal. They provide carbon-free energy for 420,000 homes.

Researched and written by World Nuclear News

Related Knowledge Center: ENERGY BASICS: nuclear

State of Play

Nuclear energy provides almost 20 percent of the U.S. electricity supply. Advocates have called for an expanded role for nuclear as an emissions-free fuel source. But the economics of building new reactors are daunting. In addition, lingering safety concerns are an institutionalized part of the calculation of nuclear regulation, and highly radioactive nuclear waste remains a can that public officials have been inclined to kick down the road. The Energy Information Administration projects a sharp decline in nuclear power generation over the next decade, as new nuclear plants — two are planned — are more than offset by anticipated retirements of several operating reactors.

More informationabout ENERGY BASICS: nuclear