Texas Liquefied Natural Gas Permit Vacated By Fifth Circuit

The Fifth Circuit wiped out a permit for a liquefied natural gas plant and export terminal in Port Arthur, Texas, after holding a state agency reversed course without proper explanation.

The Texas Commission on Environmental Quality didn’t impose certain emissions limits on the Port Arthur facility proposal that it imposed on a similar one, which contravened its own precedent. When that happens, adequate reasoning is required, but the commission didn’t provide any, the US Court of Appeals for the Fifth Circuit said Tuesday.

During proceedings before administrative law judges, the Port Arthur Community Action Network challenging the permit approval pointed ...

Related Knowledge Center: Liquefied natural gas

State of Play

Driven by plentiful natural gas produced from shale plays, the United States began exporting liquefied natural gas in 2016 when the Sabine Pass terminal in Louisiana opened and shipped its first cargo. Since then, additional capacity, or trains, have been added to Sabine Pass, and terminals have become operational in Cameron Parish, La.; Hackberry, La.; Cove Point, Md.; and Corpus Christi, Texas. The Energy Information Administration projects that U.S. LNG export capacity will reach 8.9 billion cubic feet per day (Bcf/d) by the end of 2019, making it the third largest in the world, behind Australia and Qatar. The tariff war with China has the potential to impact some final investment decisions for additional terminals in the coming months.