Snowy Hydro 2.0 project hit by delay of up to two years and another cost blowout
Snowy Hydro 2.0 project hit by delay of up to two years and another cost blowout | Energy | The Guardian
The multibillion dollar Snowy Hydro 2.0 development, billed as vital to support the transformation of Australia’s east coast electricity grid, will be delayed by up to two years and face another cost blowout.
It follows a series of problems with the development, including a tunnel-boring machine becoming stuck about 70 metres below the surface, the collapse of one of the project’s contractors and delays related to Covid-19.
In a statement on Wednesday, the federal government-owned company said its management team was “working towards resetting the delivery timeline and budget” for the pumped hydro project. It expected a delay of one or two years, pushing the earliest start date to the second half of 2028 and the completion of all units to the end of 2029.
The statement did not include an updated cost. The expected bill for the project had already blown out from $2bn when it was announced by then prime minister Malcolm Turnbull in 2017 to $5.9bn before the latest delay.
Snowy Hydro’s new chief executive, Dennis Barnes, said he was focused on ensuring the company’s major projects were “placed on a realistic and sustainable footing, while maintaining construction progress”.
“I am committed to being transparent about our progress and how we are proactively managing the inevitable issues and challenges that arise in a complex project like this,” he said.
Sign up for Guardian Australia’s free morning and afternoon email newsletters for your daily news roundup
Snowy 2.0 is promised to provide 2 gigawatts of storage to the national electricity market to help backup a system increasingly dominated by solar and wind energy. The finished project would pump water to the highest reservoir in a linked system during periods of cheap electricity and release it when required.
The delay is likely to spark fresh concerns about whether the national electricity market will have enough capacity in place to ensure electricity supply and keep power prices at an affordable level when several ageing coal-fired power plants are due to stop operating later this decade.
There is ongoing debate over whether the giant Eraring coal plant in New South Wales should have its life extended beyond its scheduled closure in August 2025. The Albanese government has promised the national grid, which supplies the five eastern states and ACT, will be running on 82% renewable energy by 2030.
skip past newsletter promotion
after newsletter promotion
Work on Snowy 2.0 stopped last year after a tunnel collapsed as a boring machine, nicknamed Florence, hit unexpectedly soft rock near Tantangara site in the Snowy Mountains.
Barnes told the ABC’s RN Breakfast that the machine’s progress was “still at 1%”, but progress was expected in “weeks, not months”.
Snowy Hydro said it expected further details on the cost of the “project reset” would be known by about July.
Related Knowledge Center: Climate economics
Climate change is now a driver of the world’s economy. The impact is profound:
- Catastrophic weather events — hurricanes, floods, droughts, high temperatures — are more frequent and more extreme. The cost can be measured in both the initial damage caused and the longer-term impact on the economy.
- Vulnerable communities are increasing climate-related investments, hardening infrastructure and taking other protective measures.
- Investment in carbon capture and storage technologies is increasingly rapidly.
- Governments are making investments and crafting regulations to reduce emissions of carbon dioxide and other greenhouse gases.
On top of all of this is the cost of uncertainty. As the Fourth National Climate Assessment, released in 2018 by the U.S. Global Change Research Program, says, “The assumption that current and future climate conditions will resemble the recent past is no longer valid.”