Poland's R.Power announces 55-MWp solar farm project in Romania

Renewables Now · last updated

The Lazuri Solar Park will be located in Satu Mare County and is expected to begin construction in the third quarter of 2025, with energisation scheduled for the third quarter of 2026, the company said in a press release.

The plant will be connected to Romania’s national grid via a newly constructed 110 kV loop-in/loop-out switching station integrated into the existing Vetis–Abator overhead line.

R.Power estimates the solar farm will generate around 70 GWh of electricity per year, sufficient to power more than 48,000 households.

Download SeeNext’s analysis of the renewable energy industry in Southeast Europe here.

Lazuri is one of four R.Power projects, with a combined capacity of 85 MWp, that secured 15-year contracts for difference (CfD) in Romania’s renewables auction.

“This project not only supports Romania’s ambitious renewable energy targets but also marks a strategic milestone in strengthening our presence in key Eastern European markets,” said Katarzyna Suchcicka, Vice President of R.Power.