Georgia Power files RFP for up to 6,000MW of new dispatchable energy resources
The utility also filed a separate request to certify an additional approximately 385MW of new supplemental solar resources as part of the Clean and Renewable Energy Subscription (CARES) 2023 programme.
The CARES programme allows commercial and industrial (C&I) customers to purchase a subscription for a share of a project’s renewable electricity generation. In September 2025, Georgia Power certified five solar power purchase agreements (PPAs) within its borders, for a combined capacity of just over 1GW.
Georgia Power claims that currently, 32 large-load customers have committed to receiving approximately 15,600MW of electric service with 21 projects under construction.
This RFP builds on the utility’s previous approval from the Public Interest Advocacy (PIA) staff of the PSC for 9,900MW of new generation resources, including more than 3GW of battery storage that the utility would own.
The company further claimed that following the PSC’s approval of updates to rules and regulations for Georgia Power in 2025, “potential large-load customers must now meet more stringent criteria, including providing financial commitments and demonstrating infrastructure readiness, to remain in the company’s long-term development pipeline.”
In February of this year, the US Department of Energy (DOE) closed a US$26.5 billion loan package with two wholly owned subsidiaries of utility Southern Company, in Georgia and Alabama.
Georgia Power, which is Southern Company’s Georgia-based subsidiary, did not share specifics for its loan from the DOE. However, in its 2025 integrated resource plan (IRP), the company considers multiple types of energy storage, including lithium-ion (Li-ion), CAES, and pumped hydro.
Both Georgia Power, and the state as a larger apparatus have also shown considerable interest in advancing BESS projects.