Europe To Face Offshore Wind Tower Deficit By 2028

OilPrice · OilPrice.com · last updated

Europe To Face Offshore Wind Tower Deficit By 2028 | OilPrice.com

Offshore wind developments are a critical component of Europe’s energy transition plans, but a supply headache could be on the horizon for the industry before the end of the decade. Rystad Energy’s modeling shows that in 2028, demand for offshore turbine towers will outstrip manufacturing capacity, signaling that time is running out for the continent to address the issue and ramp up production capabilities.

Rystad Energy’s offshore wind capacity outlook shows that wind tower manufacturing capacity will keep pace and exceed demand before 2028. However, that year is the turning point, and in 2029, demand will surpass manufacturing capacity by a significant margin. Steel demand for offshore wind towers will total more than 1.7 million tonnes in 2029, but manufacturing capacity will be a maximum of around 1.3 million tonnes, meaning supply can only meet about 70% of demand.

If Europe is to reverse this trend, manufacturers need to initiate expansion in the next two years, since it takes between two and three years to build new facilities. These forecasts assume no major steel shortage, so manufacturers can work at full capacity. If a shortage materializes, Europe could face a supply issue even earlier than expected.

Turbine sizes keep growing as the importance of offshore wind to the global power grid accelerates, and tower demand is projected to surge accordingly. This is a golden opportunity for manufacturers to capitalize on increased demand, but new capacity needs to be added imminently if Europe is going to avoid a supply headache.

Alexander Flotre, vice president, Rystad Energy

Learn more with Rystad Energy’s Wind Solution.

Since constructing a tower manufacturing facility can take three years, European producers must initiate more expansions within the next two years, at the latest. They should not find this problematic as wind towers are made of steel, with no particularly complex or specialized machinery required.

While the average turbine capacity fixed in Europe in 2023 is expected to reach almost 10 megawatts (MW), Rystad Energy estimates that 50% of the total turbines installed between 2029 and 2035 will be bigger than 14 MW, with some projects forecasting to build 20-MW at the beginning of 2030.

It is instructive to note that a tower’s weight varies with the hub height, which is required to be more than half of the rotor diameter – excluding the clearance to the water surface – and which fluctuates from country to country.

In addition, as rotor dimensions grow, turbine sizes increase and larger towers are required. This growth is more prominent in Europe, where offshore wind developers have requested turbines of 12 MW or larger for their projects.

Spain and Denmark lead European offshore wind tower supply, accounting for about 90% of the estimated 1.1 million tonnes of the continent’s supply.

ADVERTISEMENT

By Rystad Energy

More Top Reads From Oilprice.com:

Where Are Oil Prices Going? It's Complicated
Energy Regulator Claims Canadian Oil Production Will Plunge 76% By 2050
Sanctioned Goods Are Sneaking Into Russia Through Kazakhstan

Related Knowledge Center: Offshore wind energy

State of Play

Over the next decade, U.S. offshore wind power is expected to grow from a single 30-megawatt wind farm off Rhode Island to more than 2,000 MW of capacity along the Atlantic Seaboard. There are contracts for wind power off the coasts of Massachusetts, Connecticut, New York, Maryland, New Jersey, Rhode Island, and Virginia.

The National Renewable Energy Laboratory has estimated the United States has over 4,000 gigawatts (GW) of offshore wind potential, enough to power the country four times over.

The growth in part being spurred by state solicitations, including in New York, where then-Gov. Andrew Cuomo (D) set a commitment of 9,000 MW of offshore wind by 2035, and in Connecticut, where in June 2021, Gov. Ned Lamont (D) signed legislation authorizing the construction of 2,000 MW of offshore wind by 2030.

The offshore development is also being driven by an investment tax credit set to end in December 2019 and is equal to 12 percent of expenditures. U.S. Sens. Susan Collins (R-Maine) and Tom Carper (D-Del.) have introduced a bill to extend the tax credit for up to eight years.

The Interior Department has held eight competitive lease sales that resulted in 15 offshore wind leases over 1.7 million acres that has the potential for 21 GW of capacity. In February 2022, the Bureau of Ocean Energy Management completed a bidding process that realized $4.37 billion for 488,000 acres across six lease areas in federal waters off New York and New Jersey.

Projects have also been proposed off the Southeast coast, off California and Hawaii, and for the Great Lakes.

More informationabout Offshore wind energy