Denmark's North Sea energy island facing more delays amid high costs

Wind Power News & Analysis RSS Feed · last updated

Denmark's North Sea energy island facing more delays amid high costs | Windpower Monthly

Lars Aagaard, the Danish energy minister, confirmed a delay to the project in a LinkedIn post on Wednesday (22 August), where he cited high costs as a key factor in the decision.

“We should not carry out the project at any price… Last summer, the bill for the original project was more than DKK 50 billion (€6.7 billion) for the treasury. That has never been the political intention,” Aagaard said.

“When we have spent time changing the project, the time for a possible realisation is pushed out in time. This hardly comes as a surprise to anyone. That's the reality,” he added.

The original estimate for the energy island’s completion was 2033. The Reuters news agency reported Aagaard as saying the date had now been pushed back to 2036.

Aagaard’s confirmation of a longer estimated timeline for the project is the latest in a series of delays, which previously saw the tender for the energy island postponed last year.

The Energiø Nordsø energy island aims to connect up to 3GW of offshore wind capacity in Denmark, allowing for export across the North Sea to neighbouring countries.

Uncertainty over Belgian participation

The project had initially been conceived as a joint venture between Denmark and Belgium, but Aagaard's post suggested that an agreement with Belgium over the future direction of the project had stalled.

“We have discussed this with Belgium right up to the Belgian parliamentary elections before the summer holidays, and we have not been able to find a way together that was sensible and acceptable to Denmark,” Aagaard stated.

Belgium’s political situation is currently in flux following parliamentary elections referenced by Aagaard, which handed no party a majority and have led to ongoing negotiations between major political parties in the country to form a coalition government.

Belgium is developing its own North Sea energy island with the Princess Elisabeth project through the country's transmissions operator, Elia. The energy island aims to connect up to 3.5GW of planned offshore wind farms in the region that Belgium plans to auction through a two-sided contract for difference (CfD) auction mechanism.

Aagaard said Energiø Nordsø could still continue with Belgian cooperation as originally planned, but that this depended on political developments in the country.

“If a new Belgian government (when one is in place...) at some point knocks on our door and agrees to a more balanced distribution of the project's costs and benefits, then our door is of course open. This must be done on the Belgian initiative,” he said.

The energy minister said Germany was interested in using power from the energy island and that Denmark would pursue cooperation with its neighbour on the project.

Related Knowledge Center: Climate economics

State of Play

Climate change is now a driver of the world’s economy. The impact is profound:

  • Catastrophic weather events — hurricanes, floods, droughts, high temperatures — are more frequent and more extreme. The cost can be measured in both the initial damage caused and the longer-term impact on the economy.
  • Vulnerable communities are increasing climate-related investments, hardening infrastructure and taking other protective measures.
  • Investment in carbon capture and storage technologies is increasingly rapidly.
  • Governments are making investments and crafting regulations to reduce emissions of carbon dioxide and other greenhouse gases. 

On top of all of this is the cost of uncertainty. As the Fourth National Climate Assessment, released in 2018 by the U.S. Global Change Research Program, says, “The assumption that current and future climate conditions will resemble the recent past is no longer valid.”