Data center-driven power crunch prompts planning for new, high-voltage lines - Prince William Times

Prince William Times · last updated

Power crunch prompts planning for new, high-voltage lines | News | fauquier.com

Dominion and PJM were slow to catch on to zooming power needs driven by data centers. This graph shows how far off early forecasts were for the coming 15 years. PJM adjusted its 15-year forecast (dotted line) this spring. Note: numbers of the left axis represent peak load; 43K means 43,000 megawatts of power.

Source: Dominion Energy Source: Dominion Energy
"Wheeler to Warrenton" opposition: A sign erected by opponents of the proposed "Wheeler to Warrenton" transmission line. The line would run from a substation near the Prince William-Fauquier county lines at Vint Hill, dubbed "the Wheeler substation" to a substation in Warrenton. Staff Photo

Related Knowledge Center: ENERGY BASICS: electricity

State of Play

Electricity is a secondary energy source: it is generated through the conversion of primary energy sources such as natural gas, coal, solar, hydropower, and wind. Electricity’s versatility is not cost-free: a substantial amount of energy is lost in its generation and the cost of storage is high, compared with fuels such as coal, oil and natural gas. The economics of battery technology hold the key to expanded use of renewable sources to generate electricity.

More informationabout ENERGY BASICS: electricity