Bullish Sign for Natural Gas Infrastructure as FERC Clears Path to Rev Up Construction

Natural Gas Intelligence · last updated

Legal challenges will not prevent natural gas infrastructure from moving forward under revamped orders by FERC.

A graph showing current and projected U.S. power generation resources by capacity and resource type

In a positive change for infrastructure sponsors, the Federal Energy Regulatory Commission has temporarily waived Order No. 871. The order, one of two recently issued by the Commission, was designed to balance a developer’s interest to proceed with construction, while giving stakeholders 30 days to file challenges (Nos. CP25-208-000, RM25-12-000, RM25-9-000 and CP25-499-000).

That 30-day challenge is off the table under the temporary waiver – and FERC would like to make it permanent. Eliminating the order, last updated in 2021, would “avoid delaying natural gas infrastructure projects that FERC has found are needed.”